Effects of Design Quality on Delay in Residential Construction Projects

Authors

  • Ibrahim Mahamid University of Hail

DOI:

https://doi.org/10.5755/j01.sace.28.1.20531

Keywords:

buildings, delay, design, quality, time overrun

Abstract

This study is conducted to establish the effect of design quality on project delay in building projects. It aims at: 1) investigating the major factors of design quality, 2) identifying the main delay factors in building projects, 2) establishing the relationship between design quality and delay in building projects. To achieve these objectives, a questionnaire survey is performed. Seventeen (17) factors that might affect design quality, and 15 delay factors are listed in a questionnaire form. Sixty (60) contractors and 40 consultants are asked to identify the severity of the identified factors. Results indicate that the top factors affecting design quality are: delay in payments by client for design services, staff allocation for many projects at the same time, copying and modifying from previous work to minimize time and cost, tight design schedule, lack of designer knowledge with techniques and materials available in the market. The study also concludes that the top five delay factors include: payments delay, poor labor productivity, lack of skilled manpower, frequent change orders and rework. Regression analysis for data collected from 36 building projects shows a good correlation between design quality and delay in projects. This study is the first one that addresses the problem of design quality in the West Bank in Palestine. Furthermore, it is the first study that addresses the effect of design quality on project delay in Palestine and the neighboring countries. It is hoped to be helpful for researchers and professionals to understand the impact of design quality on schedule delay.

Author Biography

Ibrahim Mahamid, University of Hail

Civil Engineering, Associate professor

Downloads

Published

2021-06-22

Issue

Section

Articles